General Information:
-
Project Dates
-
May 17th, 2022 - Preparation for construction
-
May 18th, 2022 - Phase 1 demolition begins
-
May 29th, 2022 - Edge drain being installed, preparing Hogans Way for construction
-
June 3rd, 2022 - Cobra Ct. Pour
-
Additional dates: TBD
-
Phasing map
Mailbox color code
For additional information and updates, please see below.
Current Progress
May 13th, 2022 Progress - The photos below were taken before the preparation for construction.
May 29th, 2022 Progress - Edge drain being installed, Callaway Ct. (Outer ring) in progress, Preparing Hogans Way for construction, Cobra Ct. pour on Friday, June 3rd., and a thank you to G2 for testing.
June 17th, 2022 Progress - Professionals at KCI getting the job done!
June 30th, 2022 - Updates from the community.
"There is a consistent theme here. Your guys are being universally praised for their professionalism, helpfulness and courtesy. I think it's because you guys set an example and high expectations for them. Our community appreciates all the "above the call" things you have done!" - Robert Crumley
"I just wanted to let you know, Hank Rosiek’s son and daughter were able to get him out today. The son brought him out in a wheelchair, and started to take him across, and several of the KCI workers ran over to help him. I was very impressed with their kindness, and it was very much appreciated by the family. My next door neighbors are now living at an assisted living facility. Everything at the condo will stay as is until the roads are done. I’m so happy it all worked out." - Janice Quinn
Current updates in progress and will be updated as soon as possible...